The Project:

Repairing a damaged column (hit by a forklift) in a paper recycling plant. The column was bent, The base plate was bent, All the anchor bolts were sheared.

The Process:

  • The beam was supported temporarily on both sides.
  • The damaged section was cut.
  • A new section was welded.
  • New base plate was installed.
  • New anchor bolts were installed.
  • Concrete was placed.
  • Paint was applied.